PREPA's problems mount on multiple fronts

PREPA power plant in Guayanilla
The PREPA power plant in Guayanilla. The power authority has continuing problems with outages and a sharpening cash shortage.

A raft of misfortunes and events have hit the Puerto Rico Electric Power Authority over the last 30 days that will likely affect its debt, finances, and its more than nine-year-old bankruptcy case. 

Processing Content

On Friday evening the Puerto Rico Oversight Board revoked its approval, provisionally granted in early June, for a contract with three private companies to provide temporary power generation units for 10 years. The parent company of one of the three private companies said it hadn't given its OK to the subsidiary to agree to the contract and on this basis, the board said the contract was no longer valid. The contract was for $5.9 billion over 10 years. 

In mid-July the Puerto Rico Energy Bureau ordered PREPA to transfer $100 million to LUMA, the private firm named to operate, manage, maintain, repair, and restore PREPA's transmission and distribution system, and the private generating entity Genera. However, PREPA didn't do it, saying in early August it didn't have the money and was getting perilously low on cash. 

On Aug. 5 the Puerto Rico Supreme Court accepted Puerto Rico government lawsuits from a lower court to annul the contract with LUMA and granted a 30-day period for the submission of arguments for the annulment. 

And PREPA's provision of electricity continues to be unreliable and there were two significant power outages this weekend because of lack of load capacity.

"Puerto Rico's electric power system is approaching a major crisis that threatens to further damage its operations and, more importantly, the island's economy and quality of life," said José Garriga Picó, political science professor at the University of Puerto Rico.

"PREPA's inability to comply with the Puerto Rico Energy Bureau's order to transfer $100 million to LUMA and Genera demonstrates that the nine-year bankruptcy has failed to put the utility on a stable footing or enable it to meet its current and future obligations," he said.

"The Institute for Energy Economics and Financial Analysis has been tracking PREPA's cash flow problems for many years and raised this issue before the Title III [bankruptcy] court," said Cathy Kunkel, an energy consultant at the Institute for Energy Economics and Financial Analysis. "Puerto Rico's electrical system still has not brought recurring revenues in line with recurring expenses and there is little expectation of this changing in the near future."

Municipal Market Analytics Matt Fabian said it's more of the same from the long-troubled utility.

"PREPA is already at the wrong end of the continuum from stable/predictable to unstable/unpredictable, so more potentially destabilizing news doesn't change much right away," he said. 

"PREPA's finances are now worse than before," Garriga Picó said. "If they continue to worsen, the Oversight Board would therefore have to argue for a lower recovery for creditors. Cash shortages could force deeper federal intervention, lawsuits could drag on for years, power could remain unreliable and economic investment — including large new projects that require stable electricity — could slow significantly. 

"In the coming months, PREPA will almost certainly need emergency funding from the government of Puerto Rico or the federal government," Garriga Picó said. 

"If the eventual settlement with PREPA's bondholders involves a cash payout and assuming a fair bit of that money comes from the commonwealth itself, the incremental headline impact [of recent events] is probably low," Fabian said.

"If the board winds up wanting bondholders to value and take new PREPA bonds based on the utility's standalone credit quality, these developments push down the value. But whether that means investors walk away with less or the commonwealth ultimately pays more, I don't think anyone can say," he said. 

"It's hard to see how the bankruptcy can be resolved without resolution of the [LUMA] contract issue," said Joseph Krist, publisher of Muni Credit News.

"How do you develop a reasonable plan to emerge from bankruptcy? How is it credible given LUMA's operational track record on the island?" he asked.

"The recent [10-year power generation] contract scandal shows that politically-driven contracting continues to be a poor substitute for sound electrical system planning," Kunkel said. "In this context, the PREPA bondholders' insistence that PREPA can afford to pay the entirety of the legacy bond debt while also becoming a financially stable enterprise that provides reliable electrical service to the people of Puerto Rico is absurd."

"The PREPA crisis has been managed in the worst possible bureaucratic fashion – a war of all against all – producing only delays and chaos," Garriga Picó said. "With each new crisis and controversy, the end of the PREPA bankruptcy and any real solution to the energy crisis are pushed further away.

"By now, it should be clear that PROMESA has outlived its useful life and that the [board] has become just another layer of bureaucracy that impedes prompt, effective solutions," Garriga Picó said.

"Congress should urgently consider necessary changes to give the government of Puerto Rico greater leeway. In the meantime, the board should coordinate in good faith rather than one-sidedly impose its will on the government of Puerto Rico," he said.

"Reliability, repair, maintenance all seem to be beyond LUMA," Krist said.

"A long term solution to electric service in Puerto Rico needs a serious private partner, a viable customer base and investor capital. Those aren't present right now. And the lack of reliability will continue and increase without investment," he said.

"One answer would be to create incentives for companies like they had with Section 936 of the tax code that was phased out 20 years ago but made Puerto Rico very attractive to manufacturers and pharmaceutical companies," said John Mousseau, executive vice president and chief investment officer at Cumberland Advisors. 

"With corporate involvement you can imagine some additional investment in infrastructure that the electrical system needs and that companies would demand," Mousseau said. 

"Congress doesn't want to touch this but it's hard to see progress without some federal involvement," Mousseau continued. "It may take a change in Congress and/or White House to get movement here." 

LUMA Energy took over the transmission and distribution of electricity from PREPA in June 2021. The Puerto Rico Public Private Partnership Authority and PREPA commenced a lawsuit in local court in December 2025 to declare an extension letter, signed in November 2022 with LUMA, invalid. The governor and the Puerto Rico government filed a similar suit a few days later. 

The commonwealth government has said LUMA is at least partly to blame for continuing problems with blackouts. It has given this as a rationale for seeking LUMA's ouster.

While LUMA was contacted for this story, it didn't provide comments. 

The Oversight Board, in explaining the cancellation of the private generator units, said Enchanted Rock was one of three companies involved in the deal, that the company promised to provide equipment, and signed the contract with an execution date of June 10. 

However, ERock, holding company of Enchanted Rock, said the company is not a party to the power generation project and its name and signature were used without authorization, according to the board. A Puerto Rico government office has said the contract can't be performed without Enchanted Rock's participation and so the board cancelled the contract. 

ERock didn't respond to a request for a comment.

The government is seeking temporary power generation units to provide additional load to prevent outages.

The recent PREPA developments have occurred as the authority's bankruptcy has entered a drawn out period of discovery, which started in May and is expected to continue to November. 

While the bankruptcy judge has ordered mediation, on Monday the mediation team essentially told the judge no mediation is taking place and because of this, it has paused the services of its financial advisor. 

Oral arguments on the bondholders' administrative expense claim are expected in the U.S. Court of Appeals for the First Circuit in mid-September. 

Genera didn't respond to a request for a comment. 

Meanwhile, the island is experiencing a drought and the government has instituted periodic water rationing in some areas to conserve water. Some politicians and engineers have criticized the Puerto Rico Aqueduct and Sewer Authority for failure to maintain infrastructure and prepare infrastructure for a possible drought. 


For reprint and licensing requests for this article, click here.
Trends in the Regions Puerto Rico Puerto Rico Electric Power Authority Utilities Attorneys Public finance
MORE FROM BOND BUYER
Load More