p198b6n8kv1q2m1f316pchhd1fn36.jpg

Capital Improvement

Fifteen years after opening at the site of the former Bergstrom Air Force Base, Austin Bergstrom International Airport is expanding through its $600 million capital improvement program. The project includes expansion of the terminal and aircraft apron, new baggage systems, accommodations for international flights, a new parking garage and consolidated rental car center. Image: ABIARelated Story: Austin Funds Airport Growth With $275M Deal
p198b6n8kv1262bfjhad7sfbm7.jpg
ABIA's $62 million Terminal East Infill will build a connection from the east ticket lobby to the concourse and includes a new passenger security screening checkpoint with 10 lanes and a larger customs area designed to the latest standards. Image: ABIA
p198b6n8kv1uq9b354sd1st7erh8.jpg
With the addition of seven gates, the East Infill Terminal project will include a wider concourse, new hold-room spaces, ticket lift and gate podiums, concessions and support space, duty-free concessions, restroom facilities, mechanical systems, and security systems. Image: ABIA
p198b6n8kv1u59h6k1tes11dm13ov9.jpg
The Austin airport terminal features shops and themes tied to the capital city's music and arts scene. The airport enplaned more than 5 million passengers last year and recorded its first million-passenger month in July. Image: ABIA
p198b6n8kvsc7uo51a63ra8ctsa.jpg
British Airways launched its first nonstop service to Austin from London on March 3 It was the first non-stop, trans-Atlantic flight in the capital city's history. Expansion of the Austin airport will ease customs clearance for international flights. Image: ABIA
p198b6n8kvuau1461qft4si12lkb.jpg
Construction of a new rental car facility and public parking garage is already underway, financed by bonds backed by rental car fees. The project, known as CONRAC, is scheduled for completion in 2015 at a cost of $150 million. Image: ABIA
p198b6n8kv18q11jldtme1gmba5ic.jpg
An escalator is already installed at the combined parking garage and rental car facility at Austin Bergstrom International Airport. Image: ABIA
p198b6n8kvb2g1ef61pvo1rql14mhd.jpg
The consolidated rental car facility and public parking garage is nearing completion at Austin Bergstrom International Airport. The project was financed by a separate bond issue from the $275 million of revenue bonds scheduled for sale Dec. 9. Image: ABIA